Contract Notice Detail
Summary Information

Summary Information

49,077,104.44 Dominican Pesos
 
IAD-CCC-CP-2020-0007 
CONTRATACIÓN POR LOTES DE OBRAS CIVILES, HIDRÁULICAS Y ELÉCTRICAS 
Pliego de Condiciones Específicas
Awarded
CONTRATACIÓN POR LOTES DE OBRAS CIVILES, HIDRÁULICAS Y ELÉCTRICAS 
Comparación de Precios 
Object of the Contract

Object of the Contract

Construction 
Av. 27 de Febrero, Plaza de la Bandera Distrito Nacional OZAMA O METROPOLITANA REPÚBLICA DOMINICANA  
Identification

Identification

Yes 
Scheduling

Scheduling

18/03/2020 10:30:15 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/03/2020 15:30:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
25/03/2020 13:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
27/03/2020 10:30:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
27/03/2020 11:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
27/03/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
03/04/2020 10:10:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
03/04/2020 16:10:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
08/04/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
08/04/2020 14:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
13/04/2020 10:30:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
13/04/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
20/04/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
21/04/2020 10:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
22/04/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
22/04/2020 14:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/04/2020 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
Budget Settings

Budget Settings

Operation
General Source
49,077,104.44 DOP
 DOP
AccountValueAnnual Availability
2.7.2.2.019,983,276.15  DOP----View
2.7.1.2.0114,519,152.02  DOP----View
2.7.2.1.0122,422,567.85  DOP----View
2.7.1.1.012,152,108.42  DOP----View
Payment Calendar
IDDescriptionValueMonthYear
No items found...
Certificate of Appropriation
YearCertificate CodeCertificate VersionCertificate ValueCertificate StateCertificate Link
20201149,082,104.45  DOP
Financial Settings

Financial Settings

No 
No 
Bidders Replies List

Bidders Replies List

07/05/2020 10:13:52 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
PositionAccepted?Arrival DateTimeSupplier
1Yes
27/03/2020 09:10:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
2Yes
27/03/2020 09:40:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
3Yes
27/03/2020 09:45:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
4Yes
27/03/2020 09:50:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
5Yes
27/03/2020 09:56:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Contract Documents

Contract Documents

No
Document NameType
ACTA ADMINISTRATIVA CP-2020-0007.pdfActo de Aprobación de la modalidad de contratación y selección de los peritos Download
SOLICITUD DE COMPRAS CP-2020-0007.pdfSolicitud Compra o Contratación Download
CERTIFICACION DE EXISTENCIA DE FONDOS CP-2020-0007.pdfCertificado de Apropiación Presupuestaria Download
LISTADOS DE PARTIDAS CP-2020-0007.pdfBases de la Contratación (Especificaciones / Fichas Técnicas / Pliego de Condiciones) Download
ESPECIFICACIONES TECNICAS Y PLANOS CP-2020-0007.pdfBases de la Contratación (Especificaciones / Fichas Técnicas / Pliego de Condiciones) Download
PLIEGO DE CONDICIONES CP-2020-0007 II.pdfTerms and ConditionsDownload
Award and Contract Information

Award and Contract Information

 AwardAward DateAward ValueAward State 
   DO1.AWD.80120707/05/2020 11:0348,888,167.96 Dominican PesosActive 
    Final Report:07/05/2020 11:03Download
  
    Awarded CompanyContract Value
Document(s)
 Awarded lot
    Constructora Alcar, SRL9,949,905.81 Dominican Pesos
Download
Download
Download
View Detail
 AZUA
    Concretos Nuñez Mañon Concrenuma, SRL14,176,587.65 Dominican Pesos
Download
Download
Download
View Detail
 BARAHONA
    Dotel Sierra Constructores, SRL7,800,613.01 Dominican Pesos
Download
Download
Download
View Detail
 ELIAS PIÑA
    Madera & Madera Construcciones, SRL14,809,271.25 Dominican Pesos
Download
Download
Download
View Detail
 MONTECRISTI
    Karen Estephanía Suarez Pimentel2,151,790.25 Dominican Pesos
Download
Download
Download
View Detail
 A NIVEL NACIONAL
Questionnaire

Questionnaire

 
 
 1 
Sobre 1 - Credenciales
 1.1  
ADJUNTAR DOCUMENTOS SEGÚN LAS LAS PAGINAS 30 HASTA 38 DEL PLIEGO DE CONDICIONES Esta pregunta requiere anexar documentos (ADJUNTAR DOCUMENTOS SEGÚN LAS LAS PAGINAS 30 HASTA 38 DEL PLIEGO DE CONDICIONES )
    
 
 2 
Sobre 2 - Propuesta Económica
 2.1  
 Lote 1AZUA-
    
Subtotal
9,983,276.15
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
72131601 - Construcción d(...)
2.7.2.2.01PARTIDA GENERALES 1UD7,700,174.437,700,174.43
    
 
2
72131601 - Construcción d(...)
2.7.2.2.01COSTOS INDIRECTOS1UD770,017.44770,017.44
    
 
3
72131601 - Construcción d(...)
2.7.2.2.01DIRECCION TECNICA1UD756,542.14756,542.14
    
 
4
72131601 - Construcción d(...)
2.7.2.2.01IMPREVISTO1UD756,542.14756,542.14
 2.2  
 Lote 2BARAHONA-
    
Subtotal
14,519,152.02
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
30222116 - Oficina de adm(...)
2.7.1.2.01PARTIDA GENERALES 1UD11,198,728.9111,198,728.91
    
 
2
30222116 - Oficina de adm(...)
2.7.1.2.01COSTOS INDIRECTOS1UD1,100,275.111,100,275.11
    
 
3
30222116 - Oficina de adm(...)
2.7.1.2.01DIRECCION TECNICA1UD1,119,872.891,119,872.89
    
 
4
30222116 - Oficina de adm(...)
2.7.1.2.01IMPREVISTO1UD1,100,275.111,100,275.11
 2.3  
 Lote 3ELIAS PIÑA-
    
Subtotal
7,804,530.35
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
30222207 - Presa
2.7.2.1.01PARTIDA GENERALES 1UD6,019,691.86,019,691.80
    
 
2
30222207 - Presa
2.7.2.1.01COSTOS INDIRECTOS1UD591,884.7591,884.70
    
 
3
30222207 - Presa
2.7.2.1.01DIRECCION TECNICA1UD601,069.15601,069.15
    
 
4
30222207 - Presa
2.7.2.1.01IMPREVISTO1UD591,884.7591,884.70
 2.4  
 Lote 4MONTECIRSTI-
    
Subtotal
14,618,037.50
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
30222207 - Presa
2.7.2.1.01PARTIDA GENERALES 1UD11,275,00011,275,000.00
    
 
2
30222207 - Presa
2.7.2.1.01COSTOS INDIRECTOS1UD1,127,5001,127,500.00
    
 
3
30222207 - Presa
2.7.2.1.01DIRECCION TECNICA1UD1,107,768.751,107,768.75
    
 
4
30222207 - Presa
2.7.2.1.01IMPREVISTO1UD1,107,768.751,107,768.75
 2.5  
 Lote 5A NIVEL NACIONAL-
    
Subtotal
2,152,108.42
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
72131502 - Construcción c(...)
2.7.1.1.01PARTIDA GENERALES 1UD1,643,1251,643,125.00
    
 
2
72131502 - Construcción c(...)
2.7.1.1.01COSTOS INDIRECTOS1UD164,812.59164,812.59
    
 
3
72131502 - Construcción c(...)
2.7.1.1.01DIRECCION TECNICA1UD172,085.41172,085.41
    
 
4
72131502 - Construcción c(...)
2.7.1.1.01IMPREVISTO1UD172,085.42172,085.42
Public Messages

Public Messages

TypeReferenceSubjectDate
07/05/2020 11:03 (UTC -4 hours)
Detail
07/05/2020 10:13 (UTC -4 hours)
Detail