Contract Notice Detail
Summary Information
Summary Information
Summary Information
Base Total Price:
112,423,095.56 Dominican Pesos
Request Reference:
INDRHI-CCC-CP-2023-0016
Request Name:
CONSTRUCCION MURO DE GAVION CANAL MONSIEUR BOGAERT, DIRECCION REGIONAL SISTEMA DE RIEGO ALTO YAQUE DEL NORTE, DIVISION DE RIEGO DE SANTIAGO.
Phase:
Pliego de Condiciones Específicas
State:
Awarded
Description:
CONSTRUCCION MURO DE GAVION CANAL MONSIEUR BOGAERT, DIRECCION REGIONAL SISTEMA DE RIEGO ALTO YAQUE DEL NORTE, DIVISION DE RIEGO DE SANTIAGO.
Procedure Type:
Comparación de Precios
Object of the Contract
Object of the Contract
Object of the Contract
Type of Contract:
Construction
Main Object CPV Main Category:
Av. Jimenez Moya/ Juan de Dios Ventura Siimó OZAMA O METROPOLITANA REPÚBLICA DOMINICANA
Identification
Identification
Identification
Is Public
Yes
Scheduling
Scheduling
Scheduling
Fecha de publicación del aviso de convocatoria
31/08/2023 11:02:23
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Presentación de aclaraciones
05/09/2023 16:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Plazo máximo para expedir Emisión de Circulares, Enmiendas y/o Adendas
07/09/2023 13:30:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Presentación de oferta economica
11/09/2023 11:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Apertura del Sobre Economico
11/09/2023 11:15:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Verificación, Validación y Evaluación de Credenciales/Ofertas técnicas
14/09/2023 14:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Informe Preliminar de Evaluación de Credenciales/Ofertas técnicas
14/09/2023 14:30:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Notificación de Errores u Omisiones de Naturaleza Subsanable
14/09/2023 15:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Adjudicación
18/09/2023 15:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Notificación de Adjudicación
25/09/2023 14:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Apertura Oferta Económica
26/09/2023 11:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Evaluación de Oferta Económica
04/10/2023 14:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Acto de Adjudicación
10/10/2023 14:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Notificación de Adjudicación
10/10/2023 15:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Constitución de Garantía de Fiel Cumplimiento
13/10/2023 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Suscripción del Contrato
27/10/2023 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Publicación del Contrato
27/10/2023 12:30:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Budget Settings
Budget Settings
Budget Settings
Expenditure Objective
Investment
Source of Funds
General Source
Manual Integration?
SNIP?
Snip
No
SNIP Code
14715
Budget Total Value
110,534,601.35
DOP
Budget Appropriation Value
DOP
Account
Value
Annual Availability
2.7.2.1.01
110,534,601.35
DOP
----
View
Payment Calendar
ID
Description
Value
Month
Year
1
20%
22,106,920.27
DOP
Noviembre
2023
2
1er pago
6,300,000.00
DOP
Enero
2024
3
2do pago
6,300,000.00
DOP
Febrero
2024
4
3er pago
6,300,000.00
DOP
Marzo
2024
5
4to pago
6,300,000.00
DOP
Abril
2024
6
5to pago
6,300,000.00
DOP
Mayo
2024
7
6to pago
6,300,000.00
DOP
Junio
2024
8
7mo pago
6,300,000.00
DOP
Julio
2024
9
8vo pago
6,300,000.00
DOP
Agosto
2024
10
9no pago
6,300,000.00
DOP
Septiembre
2024
11
10mo pago
6,300,000.00
DOP
Octubre
2024
12
11vo pago
6,300,000.00
DOP
Noviembre
2024
13
12 pago
6,300,000.00
DOP
Diciembre
2024
14
13vo pago
6,300,000.00
DOP
Enero
2025
15
14vo pago
6,300,000.00
DOP
Febrero
2025
16
15vo
227,681.08
DOP
Marzo
2025
Certificate of Appropriation
Year
Certificate Code
Certificate Version
Certificate Value
Certificate State
Certificate Link
2023
EG1698769015798jA0ai
1
22,106,920.27
DOP
Vencido
Link
Financial Settings
Financial Settings
Financial Settings
Define Advance Payments?
Yes
% of advance over the total contract value
20
Independent property?
Define Warranties?
Yes
Seriousness of the offer
Yes
% value of the offer
1
Compliance
Yes
Good use and right investment of the advance payment
% of advance payment
100
Warranty Start Date
18/10/2023 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Warranty End Date
18/06/2025 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Contract Compliance
% of contract value
4
Warranty Start Date
18/10/2023 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Warranty End Date
18/06/2025 12:00:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Extra-contractual civil liability
No
Bidders Replies List
Bidders Replies List
Bidders Replies List
Publishing Date
09/10/2023 11:54:38
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Position
Accepted?
Arrival DateTime
Supplier
1
No
11/09/2023 10:31:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
2
Yes
11/09/2023 10:35:00
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
3
No
11/09/2023 10:35:50
((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Contract Documents
Contract Documents
Contract Documents
Access to documents requires payment?
No
Document Name
Type
SOLICITUD DE COMPRA INDRHI-CCC-CP-2023-0016.pdf
Download
ACTO ADM. INICIO DE PROCEDIMIENTO - INDRHI-CCC-CP-2023-0016.pdf
Download
ESPECIFICACIONES TECNICAS DEL INDRHI.pdf
Download
ESPECIFICACIONES TEC. DE LAS PIEDRAS PARA SER USADAS EN GAVIONES.pdf
Download
5. FORMULARIOS.docx
Download
SNCC_C026_MDELO de Contrato_Ejecucion_de_Obras.docx
Download
PLIEGO DE CONDICIONES INDRHI-CCC-CP-2023-0016.pdf
Terms and Conditions
Download
LC MURO DE GAVIÓN CANAL MONSIEUR BOGAERT.xlsx
Other
Download
Award and Contract Information
Award and Contract Information
Award and Contract Information
Award
Award Date
Award Value
Award State
DO1.AWD.1449918
09/10/2023 13:29
110,534,601.35 Dominican Pesos
Active
Final Report:
09/10/2023 13:29
Download
Awarded Company
Contract Value
Document(s)
Constructora Ing. German A. Caraballo A. & Asociados, SRL
110,534,601.35 Dominican Pesos
Download
Download
Download
View Detail
Questionnaire
Questionnaire
Questionnaire
1
Sobre 1 - Credenciales
2
Sobre 2 - Propuesta Económica
2.1
Lista de artículos
-
Subtotal
112,423,095.56
Referencia
Código UNSPSC
Cuenta presupuestaria
Descripción
Cantidad
Unidad
Precio unitario estimado
Precio total estimado
1
30222803 - Canal de riego
2.7.2.1.01
CONSTRUCCION MURO DE GAVION CANAL MONSIEUR BOGAERT
1
PAQ
112,423,095.56
112,423,095.56
Public Messages
Public Messages
Public Messages
Type
Reference
Subject
Date
Final Report
DO1.AWD.1449918
Informe final de la selección DO1.AWD.1449918
09/10/2023 13:29
(UTC -4 hours)
Detail
Announcements
DO1.MSG.490481
La lista de oferentes del proceso INDRHI-CCC-CP-2023-0016 publicada por Instituto Nacional de Recursos Hidráulicos
09/10/2023 11:54
(UTC -4 hours)
Detail
General
DO1.MSG.482353
CIRCULAR No. 1 - INDRHI-CCC-CP-2023-0016
07/09/2023 13:42
(UTC -4 hours)
Detail