Contract Notice Detail
Summary Information

Summary Information

260,941,689.42 Pesos Dominicanos
 
ETED-CCC-LPN-2023-0015 
CONSTRUCCIÒN DE LAS LINEAS DE TRANSMISIÒN DE ENTRADA A LA NUEVA SS/EE LA VEGA 
Fase del Pliego de Condiciones Específicas
Awarded
CONSTRUCCIÒN DE LAS LINEAS DE TRANSMISIÒN DE ENTRADA A LA NUEVA SS/EE LA VEGA 
Licitación Pública Nacional 
Object of the Contract

Object of the Contract

Construction 
AVENIDA ROMULO BETANCOURT 1228 BELLA VISTA Distrito Nacional OZAMA O METROPOLITANA REPÚBLICA DOMINICANA  
Identification

Identification

Yes 
Scheduling

Scheduling

02/06/2023 10:05:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/03/2023 09:00:16 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
20/04/2023 14:30:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
05/05/2023 12:15:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
02/06/2023 10:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
02/06/2023 10:05:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
14/06/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
15/06/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
16/06/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
21/06/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/06/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
28/06/2023 10:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
19/07/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
26/07/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
02/08/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
03/08/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/08/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
24/08/2023 17:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
Budget Settings

Budget Settings

Investment
Own resources
305,718,546.00 DOP
 DOP
AccountValueAnnual Availability
2.7.2.2.01305,718,546.00  DOP----View
Payment Calendar
IDDescriptionValueMonthYear
1  AVANCE 20% 61,143,709.20  DOPOctubre2023
2  PAGO FINAL 80%244,574,836.80  DOPFebrero2025
Certificate of Appropriation
YearCertificate CodeCertificate VersionCertificate ValueCertificate StateCertificate Link
202360000021402023305,718,546.00  DOP
Financial Settings

Financial Settings

No 
No 
Bidders Replies List

Bidders Replies List

30/10/2023 13:53:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
PositionAccepted?Arrival DateTimeSupplier
1No
02/06/2023 09:38:23 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
2Yes
02/06/2023 10:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
2Yes
02/06/2023 10:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Contract Documents

Contract Documents

No
Document NameType
Tabla de cantidades.xlsOtherDownload
Tablas de Datos Técnicos.xlsxOtherDownload
ESPECIFICACIONES TECNICAS.rarDownload
PLIEGO ETED-CCC-LPN-2023-0015 CONST. L.T. ENTRADA NUEVA SUBESTACION LA VEGA.pdfTerms and ConditionsDownload
ACTA DE INICIO.pdfDownload
CF.pdfDownload
COMPROMISO ETICO.pdfOtherDownload
CONVOCATORIA FIRMADA.pdfOtherDownload
CONVOCTARIA CON FECHA.pdfOtherDownload
DICTAMEN JURIDICO.pdfDownload
SOLICITUD COMPRA.pdfDownload
Award and Contract Information

Award and Contract Information

 AwardAward DateAward ValueAward State
   DO1.AWD.146221530/10/2023 14:19305,718,546 Pesos DominicanosActive
    Final Report:30/10/2023 14:19Download
 
    Awarded CompanyContract Value
Document(s)
 
    Servinca Servicios de Ingenieria, SA305,718,546 Pesos Dominicanos
Download
Download
Download
View Detail
 
Questionnaire

Questionnaire

 
 
 1 
Sobre 1 - Requisitos Técnicos
 2 
Sobre 2 - Propuesta Economica
2.1  
 OBRAS DE ENERGIA-
    
Subtotal
260,941,689.42
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72131601 - Construcción d(...)
2.7.2.2.01CONSTRUCCIÓN L.T. 138KV Y 69KV ENTRADA NUEVA SUBESTACIÓN LA VEGA1UD260,941,689.42260,941,689.42
Public Messages

Public Messages

TypeReferenceSubjectDate
30/10/2023 14:19 (UTC -4 hours)
Detail
30/10/2023 13:53 (UTC -4 hours)
Detail
16/05/2023 17:44 (UTC -4 hours)
Detail
15/05/2023 11:52 (UTC -4 hours)
Detail
05/05/2023 16:39 (UTC -4 hours)
Detail
05/05/2023 16:37 (UTC -4 hours)
Detail
14/04/2023 11:01 (UTC -4 hours)
Detail