Contract Notice Detail
Summary Information

Summary Information

150,000,000 Dominican Pesos
 
ADN-CCC-CP-2023-0004 
“PROYECTO CONSTRUCCIÓN DE OBRAS DEL PPM 2023 EN LAS CIRCUNSCRIPCIONES 1, 2 Y 3 DEL D.N.” 
Pliego de Condiciones Específicas
Awarded
“PROYECTO CONSTRUCCIÓN DE OBRAS DEL PPM 2023 EN LAS CIRCUNSCRIPCIONES 1, 2 Y 3 DEL D.N.” 
Comparación de Precios 
Object of the Contract

Object of the Contract

Construction 
Fray Cipriano de Utera REPÚBLICA DOMINICANA  
Identification

Identification

Yes 
Scheduling

Scheduling

02/03/2023 11:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
13/02/2023 17:30:04 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
21/02/2023 11:15:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
24/02/2023 08:07:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
01/03/2023 15:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
02/03/2023 11:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
08/03/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
08/03/2023 15:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
09/03/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
14/03/2023 15:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
21/03/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
23/03/2023 11:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
04/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
05/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
11/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
17/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
19/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
20/04/2023 12:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
Budget Settings

Budget Settings

Operation
General Source
19,689,991.45 DOP
 DOP
AccountValueAnnual Availability
2.7.2.4.0119,689,991.45  DOP----View
Payment Calendar
IDDescriptionValueMonthYear
0  ADN-2023-0013719,689,991.45  DOPDiciembre2023
Certificate of Appropriation
YearCertificate CodeCertificate VersionCertificate ValueCertificate StateCertificate Link
2023ADN-CCC-CP-2023-0004202319,689,991.45  DOP
Financial Settings

Financial Settings

No 
No 
Bidders Replies List

Bidders Replies List

13/04/2023 11:53:10 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
 
PositionAccepted?Arrival DateTimeSupplier
1No
28/02/2023 10:56:57 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
2No
28/02/2023 18:56:59 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
3No
28/02/2023 23:12:03 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
4Yes
01/03/2023 08:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
5Yes
01/03/2023 08:01:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
6Yes
01/03/2023 09:15:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
7No
01/03/2023 09:27:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
8No
01/03/2023 09:43:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
9Yes
01/03/2023 09:50:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
10No
01/03/2023 10:58:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
11Yes
01/03/2023 11:07:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
12No
01/03/2023 11:16:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
13No
01/03/2023 11:18:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
14Yes
01/03/2023 11:19:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
15No
01/03/2023 11:25:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
15No
01/03/2023 11:25:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
17Yes
01/03/2023 12:29:58 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
18Yes
01/03/2023 12:40:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
19Yes
01/03/2023 13:03:03 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
20Yes
01/03/2023 13:07:16 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
21No
01/03/2023 13:26:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
22Yes
01/03/2023 13:51:08 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
23Yes
01/03/2023 14:00:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
24Yes
01/03/2023 14:10:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
25No
01/03/2023 14:16:45 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
26Yes
01/03/2023 14:31:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
27Yes
01/03/2023 14:35:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
28No
01/03/2023 14:40:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
29No
01/03/2023 14:42:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
30No
01/03/2023 14:42:03 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
31Yes
01/03/2023 14:52:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
32No
01/03/2023 14:54:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
32Yes
01/03/2023 14:54:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
34Yes
01/03/2023 14:56:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
35No
15/03/2023 14:36:00 ((UTC-04:00) Georgetown, La Paz, Manaus, San Juan)
Contract Documents

Contract Documents

No
Document NameType
ADN-CCC-CP-2023-0004-Acto Inicio de Procedimiento-PROYECTO CONSTRUCCIÓN DE OBRAS DEL PPM 2023.pdfActo de Aprobación de la modalidad de contratación y selección de los peritos Download
ADN-CCC-CP-2023-0004-Dictamen Juridico-PROYECTO CONSTRUCCIÓN DE OBRAS DEL PPM 2023.pdfActo de Aprobación de las bases de la contratación (Especificaciones / Fichas Técnicas / Pliego de Condiciones) Download
ADN-CCCP-CP-2023-0004-Convocatoria-PROYECTO CONSTRUCCIÓN DE OBRAS DEL PPM 2023.pdfOtherDownload
PLIEGO DE CONDICIONES DEFINITIVO PPM 2023 (003) (1).pdfBases de la Contratación (Especificaciones / Fichas Técnicas / Pliego de Condiciones) Download
ADN-CCC-CP-2023-0004-Solicitud de Compras_0001.pdfSolicitud Compra o Contratación Download
PPM 2023 PARA CCC 2.rarOtherDownload
Formularios Anexos.rarOtherDownload
Puerta Peatonal.pdfDownload
DETALLES JUEGOS INFANTILES EN PARQUES.pdfDownload
ADN-CCC-CP-2023-0004-Enmienda 001-PROYECTO CONSTRUCCION PPM 2023_0001.pdfDownload
ADN-CCC-CP-2023-0004-Circular de Respuesta-PROYECTO CONSTRUCCION PPM 2023 (2).pdfDownload
Award and Contract Information

Award and Contract Information

 AwardAward DateAward Value 
   DO1.AWD.136623603/05/2023 14:57138,500,647.83 Dominican Pesos 
    Final Report:03/05/2023 14:57Download
 
    Awarded CompanyContract Value
Document(s)
Awarded lot
    Dineba Diseños Interiores y Ebanisteria, SRL20,844,522.69 Dominican Pesos
  
LOTE 1
    Montval Ingeniería, SRL20,872,720.25 Dominican Pesos
Download
Download
Download
View Detail
LOTE 2
    Constructora PHD, SRL18,888,504.36 Dominican Pesos
  
LOTE 3
    Conedeca, S.R.L.18,903,760.31 Dominican Pesos
  
LOTE 4
    EEC INGENIERIA, S.R.L19,724,121.61 Dominican Pesos
Download
Download
Download
View Detail
LOTE 5
    JMéndez Construcciones, SRL 19,577,027.15 Dominican Pesos
Download
Download
Download
View Detail
LOTE 6
    Grupo Biserici, SRL19,689,991.45 Dominican Pesos
Download
Download
Download
View Detail
LOTE 7
Questionnaire

Questionnaire

 
 
 1 
Sobre 1 - Credenciales
 2 
Sobre 2 - Propuesta Económica
2.1  
 Lote 1LOTE 1-
    
Subtotal
24,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
 
1
30121601 - Asfalto
2.3.6.4.07CONSTRUCION DE ACERAS Y CONTENES, REMOZAMIENTO DEL PARQUE INFANTIL ENSANCHE QUISQUEYA, ASFALTADO DE CALLES Y SOLUCION DE DRENAJE EN LA CIRCUNSCRIPCION 1, D.N., SECTOR GAZCUE, SAN CARLOS, ENSANCHE QUISQUEYA, DON BOSCO, ZONA UNIVERSITARIA, LOS PLATANITOS, SECTOR LOS PRADITOS1UD24,000,00024,000,000.00
 2.2  
 Lote 2LOTE 2-
    
Subtotal
19,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01CONSTRUCCION DE ACERAS Y CONTENES, REMOZAMIENTO DE CLUB MULTIUSO 30 DE MAYO, REMOZAMIENTO DE CANCHA ENRIQUILLO, REMOZAMIENTO DEL CLUB JIMENEZ MOYA, CONSTRUCCION DE GRADA Y SOLUCION DE DRENAJE EN LA CIRCUNSCRIPCION 1, D.N.SECTOR CACIQUE, ENRIQUILLO, ATALA, 30 DE MAYO, INVI NUEVO NORTE, MATA HAMBRE, MANRESA ALTAGRACIA, SAN JOSE, 1UD19,000,00019,000,000.00
 2.3  
 Lote 3LOTE 3-
    
Subtotal
21,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01CONSTRUCCION DE ACERAS Y CONTENES, REMOZAMIENTO DEL PARQUE TELEVIDA Y SOLUCION DE DRENAJE EN LA CIRCUNSCRIPCION 2 y 3, D.N.,SECTOR PUERTO ISABELA, ENSANCHE LA FE, LAS FLORES DE CRISTO REY, EL CALICHE, LA ZURZA, VILLA AGRICOLAS, VILLA JUANA 1UD21,000,00021,000,000.00
 2.4  
 Lote 4LOTE 4-
    
Subtotal
21,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01RECONSTRUCCION DE CAÑADA DEL ZOOLOGICO, RECONSTRUCCION DE CAÑADA LA ESPERANZA, RECONSTRUCCION DE CAÑADA EL CLARET, REMOZAMIENTO Y ASFALTADO DEL PARQUE LA 800, CONSTRUCCION DE ACERAS Y CONTENES Y SOLUCION DE DRENAJE EN LA CIRCUNSCRIPCION 2, D.N.,SECTOR LA AGUSTINITA, LA AGUSTINA, LA ESPERANZA, LA 800, LOS PROCERES, EL CLARET, VILLA MARINA 1UD21,000,00021,000,000.00
 2.5  
 Lote 5LOTE 5-
    
Subtotal
22,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01CONSTRUCCION DE ACERAS, CONTENES Y ESCALONES, ASFALTADO DE CALLES, EN LA CIRCUNSCRIPCION 2, D.N.,SECTOR PERANTUEN, LOS PERALEJOS, LOS GIRASOLES, ALTOS DE ARROYO HONDO II, EL AGUACATE, VILLA MARIA, PALMA REAL 1UD22,000,00022,000,000.00
 2.6  
 Lote 6LOTE 6-
    
Subtotal
21,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01CONSTRUCCION DE ACERAS Y CONTENES, CONSTRUCCION DE BADENES Y REPARACION DE BARANDA PERIMETRAL CALLE NAZARET, EN LA CIRCUNSCRIPCION 3, D.N.SECTOR CAPOTILLO, SIMON BOLIVAR, LA CIENAGA, GUALEY, 24 DE ABRIL, GUACHUPITA, LOS GUANDULES,1UD21,000,00021,000,000.00
 2.7  
 Lote 7LOTE 7-
    
Subtotal
22,000,000.00
    
 
ReferenciaCódigo UNSPSCCuenta presupuestariaDescripciónCantidadUnidadPrecio unitario estimadoPrecio total estimado
    
1
72101703 - Construcción d(...)
2.7.2.4.01CONSTRUCCION DE ACERAS Y CONTENES, REMOZAMIENTO DE PARQUE, CLUB COMUNITARIO CODECA Y CASITA COMUNITARIA, REMOZAMIENTO PARQUESITO DE VILLA ELOISA, SOLUCION DE DRENAJE Y CONSTRUCCION DE BADENES, EN LA CIRCUNSCRIPCION 3, D.N.BARRIO MEJORAMIENTO SOCIAL, LAS CAÑITAS, VILLA CONSUELO, ENSANCHE LUPERON, VILLA FRANCISCA, VILLA MARIA, 27 DE FEBRERO,1UD22,000,00022,000,000.00
Public Messages

Public Messages

TypeReferenceSubjectDate
03/05/2023 14:57 (UTC -4 hours)
Detail
17/04/2023 09:32 (UTC -4 hours)
Detail
13/04/2023 11:53 (UTC -4 hours)
Detail
10/04/2023 12:40 (UTC -4 hours)
Detail
28/03/2023 12:23 (UTC -4 hours)
Detail
27/03/2023 16:29 (UTC -4 hours)
Detail
22/03/2023 09:49 (UTC -4 hours)
Detail
02/03/2023 11:42 (UTC -4 hours)
Detail
23/02/2023 21:10 (UTC -4 hours)
Detail
23/02/2023 15:36 (UTC -4 hours)
Detail
23/02/2023 15:29 (UTC -4 hours)
Detail
23/02/2023 15:24 (UTC -4 hours)
Detail
22/02/2023 16:03 (UTC -4 hours)
Detail
22/02/2023 15:42 (UTC -4 hours)
Detail
21/02/2023 11:35 (UTC -4 hours)
Detail
17/02/2023 14:40 (UTC -4 hours)
Detail